Close Menu
The Civil Engineering
  • Home
  • All Posts
  • Construction
  • Estimating
  • Road Works
  • Asphalt
  • BBS
  • Civil 3D
  • Surveying
  • QA/QC
  • Videos

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

What's Hot

Civil Engineering Basic Knowledge – Every Engineer Must Know

July 22, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023
Facebook X (Twitter) Instagram
Trending
  • Civil Engineering Basic Knowledge – Every Engineer Must Know
  • Compound Wall Estimate Guide with Bar Bending Schedule
  • Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria
  • How to Calculate Load on Footing for Structural Support
  • Calculate Bar Bending Schedule for One Way Slab
  • How to Calculate Quantity of Concrete Volume for Staircase
  • Dog Legged Staircase, Components & Design of Dog Legged Stair
  • Curing Concrete – How Long it Takes & How To Cure
The Civil EngineeringThe Civil Engineering
  • Home
  • All Posts
  • Construction
  • Estimating
  • Road Works
  • Asphalt
  • BBS
  • Civil 3D
  • Surveying
  • QA/QC
  • Videos
The Civil Engineering
Home » Method Statement for Roof Waterproofing Application System
Building Construction

Method Statement for Roof Waterproofing Application System

By Engr Waseem RajaNovember 12, 20212 Comments9 Mins Read
Facebook Twitter Pinterest LinkedIn Telegram Tumblr Email

Method Statement for Roof Waterproofing Application System

In this Article today we will talk about the Roof Waterproofing Application System | Waterproof Concrete Roof | Waterproofing in Construction | How to Waterproof Roof | Flat Concrete Roof Waterproofing | Method Statement for Roof Waterproofing | Waterproofing of Roof Slab | Roof Waterproofing Products | Waterproofing Membrane for Flat Roof

Method Statement for Roof Waterproofing:

Objective:

The objective of this method statement is to define the general guidelines for Roof waterproofing system

Purpose:

The purpose of this method statement is to describe the measures and ways of proper application of water proofing to avoid any water or moisture to penetrate the roof slab‘ Work shall be carried out as per the IFC drawing, manufacturer recommendation and project specification. Waterproof Concrete Roof

Reference and Standard:

  • Approved Material Safety & Data Sheet
  • American Society for Testing and Materials (ASTM)
  • American Concrete Institute (ACI)
  • Approved protective coating Systems (APCS)
  • Project Drawing Issued for Construction (IFC)
  • Contractor Site Safety Plan (CSSP) Waterproofing in Construction

Material Specifications for Method Statement for Roof Waterproofing Application System:

Approved Materials:

1. Primer:

It is a cold applied, general purpose roofing primer, formulated with highly pliable, flexible bitumen, select petroleum solvents and compounded with wetting and saturation additives. (M/S DERMABIT or BITUMAT or AWAZEL) Waterproofing in Construction

2. Bitumen Membrane:

Bituminous Modified membrane 3mm (Dermabit-3170/Bitumat-FiberloneHD or Polyflame/Awazel-PY30) high performance, pre-fabricated, modified bitumen membrane, consisting of proprietary waterproofing compound, reinforced with spun bonded nonwoven polyester mat. Waterproofing in Construction

3. Bitumen Membrane (Base Flashing with Granules):

Bituminous Modified membrane 4mm (M/S DERMABIT or BITUMAT or AWAZEL) is a superior, high performance, pre-fabricated, modified bitumen membrane, consisting of proprietary waterproofing compound, reinforced with spun bonded nonwoven polyester mat. Granule surfaced sheet. Waterproofing in Construction

4. Polyethylene Sheet:

150 Micron Polyethylene sheet M/S – UNITECH

5. Thermal Insulation Board:

Thermal insulation extruded polystyrene foam begin with solid polystyrene crystals. It gives greater comfort, enhances the values of buildings, high aging resistance meets requirement C578 Manufactured and Supplied by MMC or STYROFOAM or SAPTEX How to Waterproof Roof

6. Geo Textile Membrane:

140 g/m2 polypropylene needle punctured non-woven geotextile Manufactured and Supplied by M/S ALYAF or TEXOFIB or MATTEX. Waterproofing of Roof Slab

7. Aluminium Flashing:

1mm Aluminum Flashing bar – H14 Aluminum material M/S -UNITECH Waterproofing of Roof Slab

8. Sealant:

One Component Polyurethane Sealant M/S by CMCI or BASF or INSUWRAP

Site Planning and Preparation:

all about waterproofing, best roof waterproofing products, bitumen sheets roof waterproofing, bituminous membrane waterproofing method, building waterproofing, cementitious waterproofing method statement, concrete roof deck waterproofing, concrete roof sealing, concrete roof waterproofing, concrete roof waterproofing membrane, concrete roof waterproofing methods, cost of waterproofing roof in india, do it yourself waterproof deck membrane, dr fixit roof waterproofing, dr fixit roof waterproofing cost, dr fixit roof waterproofing price, dr fixit waterproofing for roof, flat concrete roof waterproofing, flat roof waterproofing, flat roof waterproofing membrane, flat roof waterproofing paint, green roof waterproofing, how to seal a flat roof, how to waterproof a roof, how to waterproof concrete roof deck, how to waterproAtement for bituminous waterproofing, Method Statement for Roof Waterproofing, method statement for toilet waterproofing, pre proof waterproofing, pvc waterproofing membrane method statement, quality waterproofing, roof deck waterproofing, roof deck waterproofing systems, roof sealant for flat roofs, roof sealing products, roof tile waterproofing products, roof treatment, roof water proof, roof water proofing, roof waterproofer, roof waterproofing, Roof Waterproofing Application System, roof waterproofing chemical, roof waterproofing cost, roof waterproofing india, roof waterproofing material, roof waterproofing materials, roof waterproofing membrane, roof waterproofing membranes, roof waterproofing methods, roof waterproofing paint, roof waterproofing products, roof waterproofing products in Pakistan, roof waterproofing services, roof waterproofing solutions, roofing waterproof, roofing waterproof membrane, roofing waterproofing materials, roofing waterproofing membrane, roofs waterproofing, rooftop waterproofing, safe work procedure for waterproofing, sealing a flat roof, sealing flat roof, self adhesive roofing waterproof membrane, sika roof waterproofing, sika roof waterproofing products, type of waterproofing, water proofing materials, water proofing roof, water proofing treatment for roof, water roofing, waterproof concrete roof, waterproof flat roof coating, waterproof material for roof, waterproof membrane for flat roof, waterproof membrane for roof, waterproof membrane for roof price, waterproof membrane roof, waterproof membranes for flat roofs, waterproof method, waterproof paint for roof, waterproof paint for roofs, waterproof roof coating, waterproof roof membrane, waterproof roof paints, waterproof roofing material, waterproof roofing membrane, waterproof steps, waterproofing applications, waterproofing building, waterproofing ceilings, waterproofing concrete roof decks, waterproofing flat roof, waterproofing flat roof coating, waterproofing flat roof deck, waterproofing flat roofs, waterproofing for roof, waterproofing for rooftop, Waterproofing in Construction, waterproofing material for roof, waterproofing materials for roof, Waterproofing Membrane for Flat Roof, waterproofing membrane for roof deck, waterproofing membrane for roof terrace, waterproofing membrane for roofs, waterproofing methodology, waterproofing methods pdf, waterproofing of roof slab, waterproofing paint for metal roof, waterproofing paint for roof, waterproofing roof, waterproofing roof decks, waterproofing roof terrace, waterproofing roofing materials, waterproofing roofs, waterproofing rooftop, waterproofing rv roof, waterproofing steps, waterproofing treatment for roof, what is waterproofing

  • New concrete shall be cured according to ACI 308 and have sufficient time allowed for drying.
  • Remove grease, oil and other penetrating contaminants. Prepare surface in accordance with ASTM D4259 (abrasive blasting, mechanical abrading or water blasting).
  • Remove concrete curing compounds if not compatible, form release material or concrete hardeners not compatible with the coating
  • Membrane and other materials shall be shifted to particular execution location.
  • Care must be Membrane stored as per manufacturers recommendation
  • Measurement shall be taken for proper cutting without wastage
  • All materials that will be used shall have approval from Client before use.
  • Workers must wear appropriate PPE before doing the job.
  • All delivery of materials shall be stacked properly.
  • Chemical substances shall be kept on the designated chemical storage area.
  • Observe chemical compatibility of substances. Waterproofing of Roof Slab

Methodology: Method Statement for Roof Waterproofing Application System

Surface Preparation

  • Light weight concrete to receive membrane shall be dry, free from dirt, grease, boulders etc.
  • If any cracks or damages found it shall be repaired by sand cement mortar prior laying membrane
  • Cant strip at edge between floor and wall shall be made around the perimeter of the roof.
  • Skirting area shall be free from concrete spillage or protrusion if the surface not smooth sanding shall be done to suit the receiving membranes
  • If wall edges are sharp sanding shall be done to make it blunt avoiding damage of Membrane. Waterproofing Membrane for Flat Roof

Application Of Roofing system

Water Proofing Membrane Application:

all about waterproofing, best roof waterproofing products, bitumen sheets roof waterproofing, bituminous membrane waterproofing method, building waterproofing, cementitious waterproofing method statement, concrete roof deck waterproofing, concrete roof sealing, concrete roof waterproofing, concrete roof waterproofing membrane, concrete roof waterproofing methods, cost of waterproofing roof in india, do it yourself waterproof deck membrane, dr fixit roof waterproofing, dr fixit roof waterproofing cost, dr fixit roof waterproofing price, dr fixit waterproofing for roof, flat concrete roof waterproofing, flat roof waterproofing, flat roof waterproofing membrane, flat roof waterproofing paint, green roof waterproofing, how to seal a flat roof, how to waterproof a roof, how to waterproof concrete roof deck, how to waterproAtement for bituminous waterproofing, Method Statement for Roof Waterproofing, method statement for toilet waterproofing, pre proof waterproofing, pvc waterproofing membrane method statement, quality waterproofing, roof deck waterproofing, roof deck waterproofing systems, roof sealant for flat roofs, roof sealing products, roof tile waterproofing products, roof treatment, roof water proof, roof water proofing, roof waterproofer, roof waterproofing, Roof Waterproofing Application System, roof waterproofing chemical, roof waterproofing cost, roof waterproofing india, roof waterproofing material, roof waterproofing materials, roof waterproofing membrane, roof waterproofing membranes, roof waterproofing methods, roof waterproofing paint, roof waterproofing products, roof waterproofing products in Pakistan, roof waterproofing services, roof waterproofing solutions, roofing waterproof, roofing waterproof membrane, roofing waterproofing materials, roofing waterproofing membrane, roofs waterproofing, rooftop waterproofing, safe work procedure for waterproofing, sealing a flat roof, sealing flat roof, self adhesive roofing waterproof membrane, sika roof waterproofing, sika roof waterproofing products, type of waterproofing, water proofing materials, water proofing roof, water proofing treatment for roof, water roofing, waterproof concrete roof, waterproof flat roof coating, waterproof material for roof, waterproof membrane for flat roof, waterproof membrane for roof, waterproof membrane for roof price, waterproof membrane roof, waterproof membranes for flat roofs, waterproof method, waterproof paint for roof, waterproof paint for roofs, waterproof roof coating, waterproof roof membrane, waterproof roof paints, waterproof roofing material, waterproof roofing membrane, waterproof steps, waterproofing applications, waterproofing building, waterproofing ceilings, waterproofing concrete roof decks, waterproofing flat roof, waterproofing flat roof coating, waterproofing flat roof deck, waterproofing flat roofs, waterproofing for roof, waterproofing for rooftop, Waterproofing in Construction, waterproofing material for roof, waterproofing materials for roof, Waterproofing Membrane for Flat Roof, waterproofing membrane for roof deck, waterproofing membrane for roof terrace, waterproofing membrane for roofs, waterproofing methodology, waterproofing methods pdf, waterproofing of roof slab, waterproofing paint for metal roof, waterproofing paint for roof, waterproofing roof, waterproofing roof decks, waterproofing roof terrace, waterproofing roofing materials, waterproofing roofs, waterproofing rooftop, waterproofing rv roof, waterproofing steps, waterproofing treatment for roof, what is waterproofing

  • The LWC surface shall be primed with the primer recommended by the manufacturer only on the junction between horizontal and vertical surface and on vertical surface for base flashing membrane
  • Waterproofing membrane installation shall be performed using cylinder fed gas torch, trowel to seal the seams of the membrane and knife for cutting.
  • For horizontal waterproofing membrane application. Two layer of 3mm thick modified bituminous membrane (DERMABIT/BITUMAT/AWAZEL) shall be first layer loosely laid on Light weight concrete adhering only on laps with an overlap of 150mm at the end and 100mm at the side. The membrane is placed in the correct torching on position then re­ rolled for about half of its length without changing its orientation, membrane is then un­ rolled again and torched on pressing the melted area against the substrate.
  • After completion of first layer, Second layer laid over the first layer with the overlap at the center of first layer, this is fully bonded to first layer, and the membrane is placed in the correct torching on position then re-rolled for about half of its length without changing its orientation.
  • The membrane is then un-rolled again and torched on pressing the melted area against the substrate.
  • Repeat till the entire length of the membrane is bonded firmly onto the first layer in the same way with an overlap of 150mm at the end and 100mm at the side.
  • For vertical application, one layer of 4mm thick modified bituminous waterproofing membrane shall be applied to all vertical surfaces of block work wall.
  • Before applying the vertical waterproofing membrane, concrete surfaces shall be primed with primer recommended by the manufacturer of the membrane
  • All areas of the membrane above ground on the vertical surface (Base Flashing) end shall be flashed with approved Metal flashing.
  • Care must be taken over heating may cause melting which will damage the membrane
  • Edge of skirting membrane shall be fixed with Aluminum Flashing plate which should be minimum 1mm thick and 50mm-60mm wide, it shall be fixed with nail and filled with One Component Polyurethane sealant at the top as approved.(M/S CMCI or BASF or INSUWRAP) Any approved sealant can be used irrelevant to the Water Proofing Membrane
  • After the completion of initial inspection for laid membrane water must be filled for Leak test. The water level at the highest point of roof shall be 5cm and left for 24hrs
  • Approval should be taken from on field engineer for No leakage before proceeding to the next step

Thermal Insulation:

all about waterproofing, best roof waterproofing products, bitumen sheets roof waterproofing, bituminous membrane waterproofing method, building waterproofing, cementitious waterproofing method statement, concrete roof deck waterproofing, concrete roof sealing, concrete roof waterproofing, concrete roof waterproofing membrane, concrete roof waterproofing methods, cost of waterproofing roof in india, do it yourself waterproof deck membrane, dr fixit roof waterproofing, dr fixit roof waterproofing cost, dr fixit roof waterproofing price, dr fixit waterproofing for roof, flat concrete roof waterproofing, flat roof waterproofing, flat roof waterproofing membrane, flat roof waterproofing paint, green roof waterproofing, how to seal a flat roof, how to waterproof a roof, how to waterproof concrete roof deck, how to waterproAtement for bituminous waterproofing, Method Statement for Roof Waterproofing, method statement for toilet waterproofing, pre proof waterproofing, pvc waterproofing membrane method statement, quality waterproofing, roof deck waterproofing, roof deck waterproofing systems, roof sealant for flat roofs, roof sealing products, roof tile waterproofing products, roof treatment, roof water proof, roof water proofing, roof waterproofer, roof waterproofing, Roof Waterproofing Application System, roof waterproofing chemical, roof waterproofing cost, roof waterproofing india, roof waterproofing material, roof waterproofing materials, roof waterproofing membrane, roof waterproofing membranes, roof waterproofing methods, roof waterproofing paint, roof waterproofing products, roof waterproofing products in Pakistan, roof waterproofing services, roof waterproofing solutions, roofing waterproof, roofing waterproof membrane, roofing waterproofing materials, roofing waterproofing membrane, roofs waterproofing, rooftop waterproofing, safe work procedure for waterproofing, sealing a flat roof, sealing flat roof, self adhesive roofing waterproof membrane, sika roof waterproofing, sika roof waterproofing products, type of waterproofing, water proofing materials, water proofing roof, water proofing treatment for roof, water roofing, waterproof concrete roof, waterproof flat roof coating, waterproof material for roof, waterproof membrane for flat roof, waterproof membrane for roof, waterproof membrane for roof price, waterproof membrane roof, waterproof membranes for flat roofs, waterproof method, waterproof paint for roof, waterproof paint for roofs, waterproof roof coating, waterproof roof membrane, waterproof roof paints, waterproof roofing material, waterproof roofing membrane, waterproof steps, waterproofing applications, waterproofing building, waterproofing ceilings, waterproofing concrete roof decks, waterproofing flat roof, waterproofing flat roof coating, waterproofing flat roof deck, waterproofing flat roofs, waterproofing for roof, waterproofing for rooftop, Waterproofing in Construction, waterproofing material for roof, waterproofing materials for roof, Waterproofing Membrane for Flat Roof, waterproofing membrane for roof deck, waterproofing membrane for roof terrace, waterproofing membrane for roofs, waterproofing methodology, waterproofing methods pdf, waterproofing of roof slab, waterproofing paint for metal roof, waterproofing paint for roof, waterproofing roof, waterproofing roof decks, waterproofing roof terrace, waterproofing roofing materials, waterproofing roofs, waterproofing rooftop, waterproofing rv roof, waterproofing steps, waterproofing treatment for roof, what is waterproofing

  • Confirming the Nil leakage at the Membrane water shall be removed and allowed to dry followed by laying Polyethylene sheet which shall be minimum 150 micron thick, lap shall be 10 cm as per manufacturers recommendation
  • After laying protection polyethylene sheet Thermal insulation shall be laid which can be PIR or XPS according to drawing and approved Thickness. Either two Layer or single layer (M/S: MMC or SAPTEX or STYROFOAM) Any manufacturers Thermal insulation can be used for any brand of waterproofing membrane
  • Thermal Insulation boards shall be cut at edges accordingly and around pipes and roof drains Waterproofing Membrane for Flat Roof

Geo Textile Installation:

  • After Thermal insulation Geo textile membrane (non-woven polypropylene) shall be laid over. Lap shall be minimum 5cm or as per manufacturers recommendation.
  • Extend the Fabric membrane above the gravel layer minimum 50mm around the perimeter Waterproofing in Construction

Aluminum Flashing:

  • Screws with minimum Spacing of 30cm installed on vertical surface
  • The polyurethane sealant used to fill top of flashing , sealant from any approved manufacturer can be used irrelevant to Thermal insulation and Bitumen Membrane

Environmental Condition:

  • Do not apply in snow, rain, fog, or mist; or when relative humidity exceeds 85 percent; or at temperatures less than 3 °F above the dew point; or to damp or wet surfaces. Roof Waterproofing Products

Handling and Storage:

  • Store under cover, out of direct sunlight and protect from extremes of temperature. In tropical climates the product must be stored in an air-conditioned environment. As with all bituminous emulsions, some settlement will occur with prolonged storage. It is therefore, necessary to invert the drums monthly to disperse the settlement.
  • Failure to comply with the recommended storage conditions may result in premature deterioration of the product or packaging. Roof Waterproofing Products

Specializing Tools and Equipment:

  • Torch heating system
  • Gas Cylinder
  • Cutting knife
  • Screw Gun
  • Paint Brush
  • Generator/Power source
  • Water Tank
  • Spade Roof Waterproofing Products

Safety: Method Statement for Roof Waterproofing Application System

  • All works shall comply with the safety procedure or instruction as set out in project safety plan and municipality rules and regulations.
  • PPE shall be worn by all staff or labourers.
  • All operatives shall be inducted before entering the site.
  • Tool box talk shall be conducted before the activity.

First Aid Measures:

  • Eye contact Flush immediately with plenty of water for at least 15 minutes. Get medical attention.
  • Skin contact: Remove contaminated clothes immediately. Wash affected area with soap and plenty of water.
  • Inhalation: Remove affected person to fresh air. If symptoms persist get medical attention.
  • Ingestion: If swallowed obtain medical attention. Wash out mouth with water. Do not induce vomiting. Obtain medical attention.

OTHER POSTS:

  1. How to Load Transfer from Slab to Beam | Formulas with Example

  2. Difference Between Slab Culvert and Box Culvert | Types of Culvert

  3. Maximum Size of Concrete Slab, Beam and Column | Calculation Formula

  4. Basic Knowledge of Brickwork | Brick Masonary | Tests or Grade of Bricks

  5. How to Calculate Superelevation in Road | Purpose | Formula | Methods


Conclusion:

Full article on Roof Waterproofing Application System | Waterproof Concrete Roof | Waterproofing in Construction | How to Waterproof Roof | Flat Concrete Roof Waterproofing | Method Statement for Roof Waterproofing | Waterproofing of Roof Slab | Roof Waterproofing Products | Waterproofing Membrane for Flat Roof. Thank you for the full reading of this article in “The Civil Engineering” platform in English. If you find this post helpful, then help others by sharing it on social media. If any formula of BBS is missing from this article please tell me in comments.

 

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleMaximum Size of Concrete Slab, Beam and Column | Calculation Formula
Next Article How to Calculate Building Excavation in Excel | Excavation as per IS Code
Engr Waseem Raja
  • Website
  • Facebook
  • X (Twitter)
  • Instagram
  • LinkedIn

Hi! Welcome to my blog. My name is Engr Waseem Raja and I’m the author of TheCivilEngineerings.com. I am a Civil Engineer by profession but I’ve specialized and taken the journey in the field of Quality Engineering. I’ve worked as a Quality Engineer & Manager in the well-known companies in the Gulf region for almost Ten years.

Related Posts

Civil Engineering Basic Knowledge – Every Engineer Must Know

July 22, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023

How to Calculate Load on Footing for Structural Support

January 14, 2023

Calculate Bar Bending Schedule for One Way Slab

August 13, 2022

How to Calculate Quantity of Concrete Volume for Staircase

July 26, 2022

2 Comments

  1. SAMUEL SAMIR ADEAB SAAD on November 13, 2022 11:23 am

    download

    Log in to Reply
    • Engr Waseem Raja on November 18, 2022 7:30 pm

      Thanks for the comments please visit more articles by clicking on “All Posts” tab of the Menu Bar

      Log in to Reply
Leave A Reply Cancel Reply

You must be logged in to post a comment.

Top Posts

Bar Bending Schedule (BBS) | BBS Step by Step Preparation | Excel Sheet

June 26, 2021

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023
Most Popular

Bar Bending Schedule (BBS) | BBS Step by Step Preparation | Excel Sheet

June 26, 20211,212 Views

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 20231,060 Views

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023967 Views

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

Recent Posts
  • Civil Engineering Basic Knowledge – Every Engineer Must Know
  • Compound Wall Estimate Guide with Bar Bending Schedule
  • Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria
  • How to Calculate Load on Footing for Structural Support
  • Calculate Bar Bending Schedule for One Way Slab
  • How to Calculate Quantity of Concrete Volume for Staircase
The Civil Engineering
Facebook X (Twitter) Instagram Pinterest YouTube Tumblr LinkedIn Reddit TikTok VKontakte RSS
  • About Us
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions
  • Contact
© 2026 The Civil Engineering. All Rights Reserved

Type above and press Enter to search. Press Esc to cancel.