The Civil Engineering
  • Home
  • All Posts
  • Construction
  • Estimating
  • Road Works
  • Asphalt
  • BBS
  • Civil 3D
  • Surveying
  • QA/QC
  • Videos

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

What's Hot

Civil Engineering Basic Knowledge – Every Engineer Must Know

July 22, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023
Facebook Twitter Instagram
Trending
  • Civil Engineering Basic Knowledge – Every Engineer Must Know
  • Compound Wall Estimate Guide with Bar Bending Schedule
  • Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria
  • How to Calculate Load on Footing for Structural Support
  • Calculate Bar Bending Schedule for One Way Slab
  • How to Calculate Quantity of Concrete Volume for Staircase
  • Dog Legged Staircase, Components & Design of Dog Legged Stair
  • Curing Concrete – How Long it Takes & How To Cure
The Civil EngineeringThe Civil Engineering
  • Home
  • All Posts
  • Construction
  • Estimating
  • Road Works
  • Asphalt
  • BBS
  • Civil 3D
  • Surveying
  • QA/QC
  • Videos
The Civil Engineering
Home » How to Calculate Building Excavation in Excel | Excavation as per IS Code
Building Construction

How to Calculate Building Excavation in Excel | Excavation as per IS Code

By Engr Waseem RajaNovember 13, 20217 Comments5 Mins Read
Facebook Twitter Pinterest LinkedIn Telegram Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

How to Calculate Building Excavation in Excel Sheet

In this Article today we will talk about the How to Calculate Building Excavation in Excel Sheet | Excavation Meaning | Earthwork Excavation Calculation | Excavation Calculator | Construction Excavation | Foundation Excavation | Footing Excavation | Excavation in Construction | Excavation Equipments

What is Excavation or Excavation Meaning?

Excavation will be understood as the process of excavating and removing volumes of earth or other materials for the conformation of spaces where foundations, water tanks, concrete, masonry, and sections corresponding to hydraulic or sanitary systems will be housed according to project plans. Excavation Meaning

There are different types of excavation:

  • Common excavation
  • Excavation on semi-hard ground
  • Excavation in rock
  • Excavation with shoveling
  • Excavation with depletion and embedding Earthwork Excavation Calculation

Excavation IS Code

IS Code 1200: Part – 1: Earthwork

IS Code 1200: Part – 27: Earth Work Done By Mechanical Appliances

Important Point of Excavation as per IS Code 

IS 1200: Part – 1

Measurement (CL: 2.3)

  • Each dimension shall be measured to the nearest 0.01 m.
  • Areas shall be worked out to the nearest 0.01 m2 and
  • Cubical contents shall be worked out to the nearest 0.01 m3. Excavation Calculator

Work to be Measured Separately (CL: 2.4)

  • Work in or under-water,
  • Work in or under foul situations,
  • Work in snow.Foundation Excavation

Excavation in Earthwork Including Rock Cutting (CL: 4.2)

  • All excavation shall be measured in successive stages of 1.5 m stating the commencing level. This shall not apply to cases where no lift is involved as in hillside cutting. (CL: 4.2.3) Foundation Excavation

Excavation Over Area (CL: 4.7)

  • Excavation exceeding 1.5 m in width as well as 10 m2on a plan, and 300 mm in depth shall be described as excavation over areas and measured in cubic meters.

Lead (CL: 5.1)

  • Distances not exceeding 250 m shall be measured in units of 50 m.
  • Distance exceeding 250 m and not exceeding 500 m shall be measured as a separate item.
  • Leads beyond 500 m shall be measured in units of 500 m,
  • That is, there will be one item for lead exceeding 500 m and not exceeding 1000 m,
  • Another item for lead exceeding 1000 m and not exceeding 1500 m and so on up to 5 km. Footing Excavation
  • Where the lead exceeds 5 km, it will be measured in units of 1 km, half km and above be reckoned as one and less than 1/2 km.  shall be ignored.

Lift (CL: 6.1)

  • Excavation up to 1.5 m depth below ground level and depositing excavated material on the ground shall be included in the item of earthwork for various kinds of soil.
  • The extra lift shall be measured in a unit of 1.5 m or part thereof.  obvious lifts shall only be measured; that is lifts inherent in the lead due to ground slope shall not be measured ( except for lead up to 250 m).
  • When the earth has to be carried over a bank/ obstruction and dumped beyond it, the lift shall be the difference in level between the center of gravity of the excavated earth and the top of bank/construction. Excavation Equipments

IS 1200: Part – 27

Measurement (CL: 2.3)

  • Each dimension shall be measured to the nearest 0.01 m where any dimension is more than 25 m it shall be measured nearest to O.1 m2,
  • Areas shall be worked out to the nearest 0.01 m2 and
  • Cubical contents shall be worked out to the nearest 0.01 m3.

Work to be Measured Separately (CL: 2.4)

  • Work in or under-water,
  • Work in or under foul situations,
  • Work under tides, and
  • Work in snow. Excavation Equipments

Embankment

  • Forming embankments and Ming shall be measured in cubic meters and shall include the formation of the slope.
  • When the material is to be deposited in layers this shall be described stating the thickness of such layer.
  • The method of consolidation shall be described. be taken in successive stages of 1.5 m starting commencing level.

How to Excavation Calculation in Excel Sheet

Required for Excavation Calculation Excel Sheet

1. Plan, Elevation, Section
2. Footing Detail Drawing 
archaeological excavation, bulk excavation calculation, construction excavation, define excavate, detailed specification of earthwork in excavation in foundation, digging a footing for a foundation, earth work excavation, earth work excavation for foundation pdf, earth work excavation quantity, earth work excavation unit, earthwork excavation, Earthwork Excavation Calculation, earthwork excavation for foundation calculation, earthwork excavation procedure, earthwork in excavation in foundation rate, excavation and foundation contractors, excavation benching, excavation business, Excavation Calculator, excavation calculator with slope, excavation companies, excavation cost per square foot, excavation equipment, Excavation Equipments, excavation estimate example, excavation in construction, excavation machines, Excavation Meaning, excavation plan, excavation service, excavation terms, excavation tools, excavation truck, excavation work, Footing Excavation, foundation excavation, house excavation, How to Calculate Building Excavation in Excel Sheet, how to calculate excavation for foundation, how to calculate excavation volume with slope, how to dig a foundation, how to estimate excavation and backfill, how to estimate excavation and backfill Philippines, manual excavation, meaning of excavation, online excavation calculator, site work excavation, spoil calculator, t rex excavation, trench calculator, trench excavation, trench excavation calculator, trench excavation cost calculator, trench protection, trenching hazards, types of excavation, volume of earthwork formula, what does excavate, what does excavate mean

Plan (Download Plan PDF File)

Footing Detail Drawing (Download Footing Plan PDF File)

No of Footing Same Size = 6 Nos.

Size of Footing = 1400 mm x 1400 mm
Size of P.C.C = (150 + 1400 + 150) x (150 + 1400 + 150) = 1700 mm x 1700 mm
Size of Soling = Same as P.C.C = 1700 mm x 1700 mm
Excavation of Hight as per Drawing from E.G.L (Existing Ground Level) = 3500 mm + 150 mm
Excavation of Hight as per Drawing from E.G.L (Existing Ground Level) = 3650 mm
Excavation size of area L x B = ( Extra length of 500mm for working space + Length of P.C.C + Extra length of 500mm for working space) x ( Extra length of 500mm for working space + Breadth of P.C.C + Extra length of 500mm for working space)
Excavation size of area L x B = (500 mm +1700 mm + 500 mm) x (500 mm + 1700mm + 500mm)
Excavation size of area L x B = (2700 mm) x (2700 mm)

Download Excavation Excel Sheet for Click Here


Building Footing Excavation Calculator:

[CP_CALCULATED_FIELDS id=”8″]

 


OTHER POSTS:

  1. How to Load Transfer from Slab to Beam | Formulas with Example

  2. Difference Between Slab Culvert and Box Culvert | Types of Culvert

  3. Quantity of Cement, Sand & Water required for Plastering Estimate

  4. How to Calculate No of Bricks in One Cft, Wall, Room and Building

  5. What is Hidden Beam or Concealed Beam | Advantages & Disadvantages

  6. How to Calculate Water Tank Capacity for Building


FAQs


How do you calculate excavation volume?

To calculate the total excavated volume of a project, the entire project is divided into several horizontal layers. The area of a typical excavated cross-section in a horizontal layer is calculated and multiplied by the thickness of the layer. Thus, the excavated volume of this layer is obtained.

How do you calculate trench excavation?

Determine the volume of the trench by using the formula: Volume = Width x Length x Depth. As an example, a trench 12 feet long with an average width of 2.3 feet and an average depth of 5 feet has a volume of (12 x 2.3 x 5) cubic feet.

What is a compacted volume?

A measure of the volume of soil (or rocks) after its placement and compaction in a fill.

How much excavation can be done in a day by JCB?

The excavation capacity of the JCB ranges from 700 cu ft. to 1100 cu ft. per hour, depending upon the type of soil & bucket capacity.

What is Earthwork in Excavation?

Earthworks are engineering works created through the processing of parts of the earth's surface involving quantities of soil or unformed rock.

Conclusion:

Full article on How to Calculate Building Excavation in Excel Sheet | Excavation Meaning| Earthwork Excavation Calculation | Excavation Calculator | Construction Excavation | Foundation Excavation | Footing Excavation | Excavation in Construction | Excavation Equipments. Thank you for the full reading of this article in “The Civil Engineering” platform in English. If you find this post helpful, then help others by sharing it on social media. If any formula of BBS is missing from this article please tell me in comments.

 

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleMethod Statement for Roof Waterproofing Application System
Next Article Bar Bending Schedule of Lintel Beam | Typical Beam | Detailed Beam
Engr Waseem Raja
  • Website
  • Facebook
  • Twitter
  • Instagram
  • LinkedIn

Hi! Welcome to my blog. My name is Engr Waseem Raja and I’m the author of TheCivilEngineerings.com. I am a Civil Engineer by profession but I’ve specialized and taken the journey in the field of Quality Engineering. I’ve worked as a Quality Engineer & Manager in the well-known companies in the Gulf region for almost Ten years.

Related Posts

Civil Engineering Basic Knowledge – Every Engineer Must Know

July 22, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023

How to Calculate Load on Footing for Structural Support

January 14, 2023

Calculate Bar Bending Schedule for One Way Slab

August 13, 2022

How to Calculate Quantity of Concrete Volume for Staircase

July 26, 2022

7 Comments

  1. Jonathan George on March 27, 2022 5:22 am

    This is good 👌👍

    Reply
    • Engr Waseem Raja on March 29, 2022 6:55 pm

      Thanks for the comments please visit more articles by clicking on “All Posts” tab of the Menu Bar

      Reply
  2. Eduardo de Castro on September 30, 2022 3:48 pm

    Very helpful. Thanks for sharing.

    Reply
    • Engr Waseem Raja on October 6, 2022 1:26 pm

      Thanks for the comments please visit more articles by clicking on “All Posts” tab of the Menu Bar

      Reply
  3. Samira begum on December 29, 2022 3:41 pm

    Very helpful, thanks for sharing

    Reply
    • Engr Waseem Raja on December 30, 2022 2:14 am

      Thanks for the comments please visit more articles by clicking on “All Posts” tab of the Menu Bar

      Reply
    • Harish nl on December 24, 2023 11:01 am

      Very useful

      Reply

Leave A Reply Cancel Reply

Top Posts

51 Most Important Points | A Civil Engineer Must Know | Basic Knowledge

August 9, 2021

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023

How to Calculate Load on Footing for Structural Support

January 14, 2023
Most Popular

51 Most Important Points | A Civil Engineer Must Know | Basic Knowledge

August 9, 202180 Views

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 202363 Views

How to Calculate Load on Footing for Structural Support

January 14, 202352 Views

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

Recent Posts
  • Civil Engineering Basic Knowledge – Every Engineer Must Know
  • Compound Wall Estimate Guide with Bar Bending Schedule
  • Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria
  • How to Calculate Load on Footing for Structural Support
  • Calculate Bar Bending Schedule for One Way Slab
  • How to Calculate Quantity of Concrete Volume for Staircase
The Civil Engineering
Facebook Twitter Instagram Pinterest YouTube Tumblr LinkedIn Reddit TikTok VKontakte RSS
  • About Us
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions
  • Contact
© 2025 The Civil Engineering. All Rights Reserved

Type above and press Enter to search. Press Esc to cancel.