The Civil Engineering
  • Home
  • All Posts
  • Construction
  • Estimating
  • Road Works
  • Asphalt
  • BBS
  • Civil 3D
  • Surveying
  • QA/QC
  • Videos

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

What's Hot

Civil Engineering Basic Knowledge – Every Engineer Must Know

July 22, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023
Facebook Twitter Instagram
Trending
  • Civil Engineering Basic Knowledge – Every Engineer Must Know
  • Compound Wall Estimate Guide with Bar Bending Schedule
  • Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria
  • How to Calculate Load on Footing for Structural Support
  • Calculate Bar Bending Schedule for One Way Slab
  • How to Calculate Quantity of Concrete Volume for Staircase
  • Dog Legged Staircase, Components & Design of Dog Legged Stair
  • Curing Concrete – How Long it Takes & How To Cure
The Civil EngineeringThe Civil Engineering
  • Home
  • All Posts
  • Construction
  • Estimating
  • Road Works
  • Asphalt
  • BBS
  • Civil 3D
  • Surveying
  • QA/QC
  • Videos
The Civil Engineering
Home » Method Statement for Installation of Anchor Bolts | Setting Out
Construction

Method Statement for Installation of Anchor Bolts | Setting Out

By Engr Waseem RajaJanuary 1, 2021No Comments6 Mins Read
Facebook Twitter Pinterest LinkedIn Telegram Tumblr Email
Share
Facebook Twitter LinkedIn Pinterest Email

Method Statement for Installation of Anchor Bolts | Anchor Bolts Fixing Methods | Setting Out of Anchor Bolts | How to Install Anchor Bolts in Concrete Foundation:

In this article we will discuss about Method Statement for Installation of Anchor Bolts | Anchor Bolts Fixing Methods | Setting Out of Anchor Bolts | How to Install Anchor Bolts in Concrete Foundations.

Method Statement for Installation of Anchor Bolts | Construction of a pre-engineered structure such as steel structure is a challenging work. It requires the full attention of qualified staff.  It also needs a qualified QAQC Engineer to inspect the work of a construction team to ensure that the completed work is fully compliant with the project requirement.

One of the most challenging jobs in the construction of steel structure is the installation of anchor bolts where it is considered to be an ankle joint of a steel column. A method statement of the installation of anchor bolt should be developed to make sure that the process is true against the approved drawing and the most important, it should be within the safe working condition. setting out,

Here is the method statement for installation of anchor bolts.

OTHER POSTS:

  • Method Statement for Asphalt Paving Works | Asphalt Concrete
  • Method Statement for Formwork, Reinforcement and Concrete Works
  • Method Statement for Concrete Repair Works | Structural Works
Method Statement for Installation of Anchor Bolts, Fixing Methods, Setting Out of Anchor Bolts, Install in Concrete Foundations
Method Statement for Installation of Anchor Bolts | Setting Out

Title: Method Statement for Installation of Anchor Bolts

Method Statement for Installation

Purpose Setting out

This method statement shows and explains the procedure must be followed to install the anchor bolts for steel columns to achieve the requirements of the project. Concrete Foundations

Reference

• Approved Anchor Bolts Shop Drawing
• Approved Material Submittal for Anchor Bolt
• Specification Section 0000 (Place specification section here)

Material

• Anchor Bolts (Size place here)
• Nut
• Washer

Manpower

• Construction Manager
• Project Engineer/ Site Engineer
• Foreman
• Surveyor and assistant surveyor
• Safety officers with helper
• Carpenters
• Skilled and unskilled labors

Equipment and Tools

• Total Station
• Level Machine
• Plywood base plates
• Spanners
• Water level
• Line dory/ Nylon chord Concrete Foundations
• Masking tape
• PPE such as safety tools such as safety ladders, warning tapes, safety sign boards …etc

Responsibilities

Construction Manager Method Statement for Installation of Anchor Bolts

• The Construction Manager is overall responsible for the implementation of method statement of anchor bolts fixation and ensures that his team of Engineers and foremen are aware of this method statement and all resources – human, material and equipment are available to carry out the work as planned and without any delay.

Project Engineer

• Provide his site engineer with approved drawings.
• Follow up the site team to use approved materials.
• To ensure all the required equipment, tools and manpower are available on the site.
• Monitor the fixation of the anchor bolts.

QA/QC Engineer

• Ensure that the site team is using approved drawings.
• Ensure that the used materials are approved.
• Check the fixed anchor bolts in the temporary plywood plate are as per approved drawings such as diameter, number, location and the space between each anchor bolt.
• Check with surveyor the required level for the anchor bolts during fixation stage.
• Check the alignment and level of the anchor bolts.
• Ensure that anchor bolts are covered properly after fixing and approval before concrete.
• Prepare the inspection request and the checklist for the anchor bolts fixing.
• Ensure the level of anchor bolts after casting the neck columns.

Safety Officer

• Ensure that all equipment are properly maintained and in safe working conditions. Concrete Foundations
• Follow up all the safety precautions during anchor bolts preparation and fixing such as wearing helmet, safety shoes, overalls, gloves, and vests.
• Ensure that the working area is barricaded and protected during the work.

Site Engineer

• Follow the approved drawings for fix the anchor bolts.
• Instruct the manpower for fixing the anchor bolts.
• Follow up the level and the alignment of the anchor bolts during fixation.
• Follow up the work to be ready for inspection.
• Prepare a daily report for the complete area of anchor bolts fixing to the project engineer.

Foreman

• Get the instructions to start fixing from site engineer.
•  Distribute the labors for the site works.
•  Supervise the labors productivity and their works.
•  Prepare all the required tools for the fixing
•  Supervise the labors during fixing

Methodology

  • Use approved drawings for work preparation.
  • Use approved materials as per approved drawings such as anchor bolts length, diameter, number, and location.
  • To fix the anchor bolts prepare a temporary wooden plate contains holes relevant to the diameter, location and number of anchor bolts as per approved drawings.
  • Fix the bolts in the temporary wooden plate accurately.
  • Prepare the axis in the top of the neck columns in order to fix the anchor bolts.
  • After survey works, start fixing the temporary wooden plate with the anchor bolts in the top of the neck columns.
  • Insert the bottom part of the anchor bolts inside the neck columns as per approved drawings.
  • After fixing the temporary wooden plates align, level and fix properly the anchor bolts as per approved drawings.
  • The surveyor has to check the alignment and the level of the anchor bolts after fixing.
  • The Engineer shall check the anchor bolts after fixing.
  • After Engineer approval cover the anchor bolts with masking tape protection before concreting.

Safety

  • All works shall comply with the safety instruction/procedure as set out in the approved project HSE plan and all safety recommendations of local authorities shall be followed.
  • All works should comply with safety procedure/instruction as set out in project safety plan.
  • Basic PPE to be worn by all staff.

Conclusion:

Full article on Method Statement for Installation of Anchor Bolts | Anchor Bolts Fixing Methods | Reinforcement in RCC Beam | Setting Out of Anchor Bolts | BB How to Install Anchor Bolts in Concrete Foundations. Thank you for the full reading of this article in “The Civil Engineering” platform in English. If you find this post helpful, then help others by sharing it on social media. If you have any question regarding article please tell me in comments.

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
Previous ArticleGeneral Specification for Residential Building | First, 2nd, 3rd & 4th Class
Next Article Method Statement for Formwork, Reinforcement and Concrete Works
Engr Waseem Raja
  • Website
  • Facebook
  • Twitter
  • Instagram
  • LinkedIn

Hi! Welcome to my blog. My name is Engr Waseem Raja and I’m the author of TheCivilEngineerings.com. I am a Civil Engineer by profession but I’ve specialized and taken the journey in the field of Quality Engineering. I’ve worked as a Quality Engineer & Manager in the well-known companies in the Gulf region for almost Ten years.

Related Posts

Civil Engineering Basic Knowledge – Every Engineer Must Know

July 22, 2023

Compound Wall Estimate Guide with Bar Bending Schedule

January 30, 2023

How to Calculate Load on Footing for Structural Support

January 14, 2023

Calculate Bar Bending Schedule for One Way Slab

August 13, 2022

How to Calculate Quantity of Concrete Volume for Staircase

July 26, 2022

Dog Legged Staircase, Components & Design of Dog Legged Stair

July 23, 2022

Leave A Reply Cancel Reply

Top Posts

51 Most Important Points | A Civil Engineer Must Know | Basic Knowledge

August 9, 2021

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 2023

Checklist for Slab Reinforcement While Casting

February 13, 2022
Most Popular

51 Most Important Points | A Civil Engineer Must Know | Basic Knowledge

August 9, 2021103 Views

Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria

January 25, 202380 Views

Checklist for Slab Reinforcement While Casting

February 13, 202272 Views

Subscribe to Updates

Get the latest creative news from FooBar about art, design and business.

Recent Posts
  • Civil Engineering Basic Knowledge – Every Engineer Must Know
  • Compound Wall Estimate Guide with Bar Bending Schedule
  • Flight of Stairs | How Many Flight of Stairs per Floor | Design Criteria
  • How to Calculate Load on Footing for Structural Support
  • Calculate Bar Bending Schedule for One Way Slab
  • How to Calculate Quantity of Concrete Volume for Staircase
The Civil Engineering
Facebook Twitter Instagram Pinterest YouTube Tumblr LinkedIn Reddit TikTok VKontakte RSS
  • About Us
  • Disclaimer
  • Privacy Policy
  • Terms and Conditions
  • Contact
© 2025 The Civil Engineering. All Rights Reserved

Type above and press Enter to search. Press Esc to cancel.